Improvements to NW Larkspur St. from NW Lake Rd. to NW Camas Meadows Dr. are underway! Take a peek at our plan for keeping you moving through this area, along with the main project points listed below.

Phase 1
> Work on the southern half of the project will begin on Jan. 28, 2019.
> Most traffic from NW 60th and NW 61st Cr. will be routed NORTH to Camas Meadows Dr.
> Residents who live south of NW 60th Ave. on NW Larkspur Street and those who live on NW 59th Cr. will continue to use NW Lake Rd. to access their homes.
> Work is estimated to last 3-4 weeks.

Phase 2
> Work on the northern half of the project will begin around Feb. 25, 2019.
> Most traffic from NW 60th and 59th Cr. will be routed SOUTH to NW Lake Rd.
> Residents who live north of NW 60th Ave. on NW Larkspur St. and those who live on NW 61st Cr. will be routed north to Camas Meadows Dr.
> Work is estimated to last 3-4 weeks.

During both phases, the existing barricade at the north end of NW Larkspur St. will be temporarily removed to allow the detours to operate properly.

This info has been shared directly with residents in the project area. We look forward to keeping the community informed as this project progresses.

Have questions? Please contact engineering@cityofcamas.us or 360.817.1561.

 

Latest News More News

Subscribe Here

Play our About Camas Video

 Sign Up for information about emergencies and other important community news.

     Download Our Mobile App and Stay Connected!
           CamasConnect24/7

  Get up-to-date City News!  Make a service
  request, pay a utility bill, register for activities,
  view Council Meetings, and much more!   

  

  



 
My Camas
Go to top