Utility Bridge over the Washougal River
placed 8/14/08
Weekly
Updates for Public Works Projects
Current Events
This page is updated weekly based on staff meeting
notes. We try to reflect the most current status
of construction projects and how they may effect
the citizens of Camas. In reading these notes,
please remember that they reflect the best information
we have at the time of publication. Construction
activity has many variables that can change
or delay projected schedules. The Engineering
Dept. strives to provide notice 24 hours prior
to construction to adjoining neighbors through
a number of methods, which include mailings,
door hangers, and in some cases, phone calls.
2009 Goot Park CDBG Improvements
This project is partially funded through the American Recovery and Reinvestment Act and the Community Development Block Grant Program with funds obtained from the U.S. Dept. of Housing and Urban Development (HUD). The bio-catch basin, benches and bike rack have been delivered and will be installed. The swing set will be installed as it becomes available from the vendor. The restroom construction is anticipated to begin in January once the kit of materials arrive from the restroom vendor. City contact is Steve Durspek, Project Engineer and John Adams, Project Inspector. 12/10/09
Camas High School Stadium
(Replacing existing football stadium at NE 22nd and Ione)
Demolition work has been completed. Work is underway on the storm system and grading for the stadium. Team Construction LLC is the contractor for this project. Team Construction LLC is the contractor for this project.
City contact is Norm Wurzer. 01/17/10
Lacamas Lake Pier Replacement
(NW Natural Gas Line and City of Camas Water Main Supports at Lacamas lake)
The contractor has finished installing the concrete base for this project. The second and final pour is currently scheduled for this Friday (10-2-09) between 10 a.m. and noon. Traffic control will be the same on Friday as it was for today--one lane closed with flaggers at both ends directing traffic through the work area. Please call John Adams. 10/1/09
Fisher Creek Campus
(located between NW Pacific Rim Boulevard
and
NW 38th Avenue)
Site construction work has been stopped at this
time. The contractor has been onsite to correct
some erosion/washout issues. Upkeep of the erosion
control BMP (Best Management Practices) does
continue. Wubben Excavating & Underground
is the prim contractor for this project. City
Contact is Norm Wurzer. 1/07/10
Osprey Landing
(located near the city limits on the Evergreen
Hwy)
A stop work order has been issued for this site.
Monitoring for erosion control concerns continues.
The December onsite meeting with the Department
of Ecology was completed. Additional erosion
Best Management Practices were completed along
with chaining off the entrance to impede the
dumping of trash. City contacts are Wes Heigh
and Norm Wurzer. 1/07/10
Hayes Freedom High School
(east side of Helen Baller School on Ione
Street)
Work continues on the construction of the main
building. Work has also been completed on a
portion of the site's storm water system. Team
Construction LLC is the contractor for this
project. City contact is Norm Wurzer. 1/07/10
WS 687 2009 STEP / STEF Tank Pumping
All tank pumping completed for 2009. 1/13/10
City contacts are Steve Durspek or Jim Hodges
2010
Knights
Court Condominiums
(located across from the Sharp Electronics
entrance on
NW Pacific Rim Boulevard)
This project is inactive, erosion control monitoring
is ongoing. The site contractor is Scott's Excavating,
Inc. City contacts are Norm Wurzer or Wes Heigh.
10/15/09
P-826
Verizon - Fiber-to-the-Premises (FTTP)
Directional boring continues in Sunningdale
Gardens and Summit Oaks development areas. The
contractor has been responding to a number of
citizen complaints. Feedback from the citizens
has been positive after contact. The contractor
for the directional boring work is Tetra Tech.
City contacts are Norm Wurzer or Wes Heigh.
1/07/10
Deerhaven Subdivision
(on Leadbetter Road just north of
SR-500)
This project is on developer hold. If there are questions pertaining to this project, please contact Wes Heigh.1/1/10
Drewf's Farm
(located off NW Hill Street off NW Fargo)
This site has been quite active with site grading modifications and associated erosion control activities. City contact is Norm Wurzer. 1/07/10
LaDonna Subdivision
(located on the corner of Ilwaco
and McIntosh)
Sporadic work continues with the majority related to erosion Best Management Practices. East Wind Construction Co. is the contractor for this project. City contact is Norm Wurzer. 1/07/10
Logan Place
(west of the Shell Station at the
top of Prune Hill)
This project is currently on developer
hold.
If there are questions pertaining to this project, please contact Wes Heigh. 1/1/10
Province
Estates
(east of NE Province Dr. off Crown
Rd)
This site has been inactive, erosion control monitoring is ongoing. Green Construction is the primary contractor for this 40 lot development.
City contact is Norm Wurzer 10/30/09
Vista
Pointe
(near NW Astor St/NW 18th Ave)
Limited work has resumed on this site. The ADA ramp and sidewalk has been poured at the corner of NW 18th and
NW Astor. City contact for this project is Norm Wurzer. 11/25/09
Union Self Storage