APPLICATION
AND SUBMITTAL PROCEDURES
FOR RESIDENTIAL CONSTRUCTION
A
pre-application
form should be filled out and returned to the Building
Department at least 24 hours prior to submitting plans
and other required information. The pre-application
form may be mailed, hand-delivered, or faxed to 834-8863.
REQUIRED
ITEMS FOR APPLICATION
- 2
sets of plans (necessary whether you have built this
same plan in Camas before or not).
-
2 plot plans (with legal description, lot dimensions,
to scale of not less than 1”=20’).
- 2
sets of truss engineering and layouts (if you are
using trusses).
- 2
sets of engineered floor joist / I- joist drawings.
(if you will be using them).
-
1 proof of ownership.
- 1
copy of your contractor's license.
- 2
sets of lateral engineering for a 3 second wind gust of 110 miles per hours (if required due to number of
and placement of windows).
OTHER
ITEMS THAT MAY BE REQUIRED:
- For
Accessory Dwelling Units (ADU) convenant will need to be recorded.
- For
alterations/remodels -a floor plan showing new work.
- Construction near river/lake - flood plain elevation certificate.
- Consturction on fill or slopes - soils report/survey.
PLEASE NOTE:
- Payment
of the plan review fee is required at time of plan
submittal.
-
All plan reviews will be done in the order that they
are received.
-
Complete information must be submitted before the
plans can be reviewed in a timely manner.
-
If major changes are made to the plans while they
are in the review process, or there is a change in
the site location, the original application will be
cancelled. A new application will be required and
the review process will start new again.
|
|
|